Auto-populate standard start and end dates in project templates
Kaylin Graber
I manage multiple projects with similar timelines and tasks, such as bathroom remodels. It would be beneficial if I could set standard start and end dates in a project template. For instance, a task should start 3 days from the project start date and end 5 days after. This feature would automatically adjust dates for each new project based on the set start date, reducing repetitive work.
T

Tim Macchi
When creating a project from a template, you can choose a new project start date and TeamGantt will schedule the template from that date. These steps show how to create and use a template: https://teamgantt.helpscoutdocs.com/article/19-templates. If your task offsets aren’t being preserved, please let us know because that would be different from the intended workflow.