Adjustable Calendar View for Weekly Construction Schedule
Jay Trommel
I cannot adjust the calendar view to show one week with all tasks per day for each project, which would be ideal for creating a weekly construction schedule. Although the Gantt Chart view offers this option, it is too complicated for my team to interpret. The calendar view is more team-friendly, but it lacks the ability to change print settings. It would be beneficial to have an adjustable calendar view that allows for easy printing and sharing with the team.
T

Tim Macchi
Thanks for the construction scheduling context. It sounds like you may be looking for a weekly lookahead-style schedule that’s easier for the team to read than the full Gantt chart.
TeamGantt does include Lookaheads in the Construction Edition, which let you choose a start date and a 2-6 week window so only tasks that start, end, or cross that period are shown. This article walks through it: https://support.teamgantt.com/article/166-lookaheads
We’re still tracking the request for more control over a weekly, field-friendly calendar/print view with the right task detail per day.